BAPPENAS launch PPP priority project list for 2015

BAPPENAS, Indonesia's planning ministry, has published their list of priority PPP projects for 2015 by publishing BAPPENAS ministerial decree number 82/M.PPN/HK/05/2015 concerning the determination of the list of planned infrastructure projects for 2015

With 6 "ready to offer" projects this year, they're doing better than they were in the last book, launched in 2013, when they had zero projects in that category*. BAPPENAS do not appear to have launched their PPP book providing further details on the projects yet.

Indonesia has struggled in implementing its PPP agenda to date. So far, only one project has reached financial close (Central Java Power Plant), and no others have reached the award stage. Those currently under procurement do not appear likely to make it out the other end any time soon.

The reasons for the lack of success are varied and complex, but it all boils down to a lack of political commitment. I am hoping that this decree spurs more action than we have seen from the last few.

I list the projects from the decree below.

Ready to offer projects

I.1. TRANSPORTATION

I.1.1. Sea Transportation

Not Available

I.1.2. Air Transportation

Not Available

I.1.3. Railway

1. Soekarno-Hatta International Airport – Halim Railway

2. Bandung Light Rail Transit (LRT), West Java

3. Tanjung Enim – Tanjung Api-Api Railway, South Sumatera

I.1.4. Land Transportation

Not Available

I. 2. TOLL ROAD

Not Available

I.3. WATER SUPPLY

1. West Semarang Municipal Water Supply, Central Java

2. Pondok Gede Water Supply, Bekasi

3. Pekanbaru Water Supply, Riau

I.4. SANITATION

Not Available

I.5. TELECOMMUNICATION

Not Available

I.6. ELECTRICITY

Not Available

I.7. OIL AND GAS

I.7.1 Transmission

Not Available

I.7.2 DISTRIBUTION

Not Available

Prospective projects

II.1. TRANSPORTATION

II.1. 1. Sea Transportation

Not Available

II.1. 2. Air Transportation

Not Available

II.1. 3. Railway

1. Integrated Terminal of Gedebage (Railway), West Java

2. Development of South Sumatera Monorail

II.1. 4. Land Transportation

Not Available

II.2. TOLL ROAD

1. Manado – Bitung Toll Road

2. Tanjung Priok Access Toll Road

3. Balikpapan – Samarinda Toll Road

4. Cileunyi – Sumedang – Dawuan Toll Road

5. Pandaan – Malang Toll Road

II. 3. WATER SUPPLY

Not Available

II.4. SANITATION

Not Available

II. 5. TELECOMMUNICATION

Not Available

II. 6. ELECTRICITY

1. Karama Hydro Power Plant, West Sulawesi

II. 7. OIL AND GAS

II. 7.1. Transmission

Not Available

II. 7.2. Distribution

Not Available

Prospective projects

III.1. TRANSPORTATION

III.1.1. Sea Transportation

1. Development of Maloy International Port, East Kalimantan

2. Expansion of Kabil Port (Tanjung Sauh Terminal), Riau Island

3. Development of Kuala Tanjung International Hub Port

4. Development of Bitung International Hub Port, North Sulawesi

5. Development of Makassar New Port, South Sulawesi

6. Development of Baubau Port, Southeast Sulawesi

7. Development of Garongkong Port, South Sulawesi

III.1.2. Air Transportation

1. Development of New Bali Airport, Bali

2. Kulonprogo International Airport, DI Yogyakarta

3. Expansion of Mutiara Airport, Central Sulawesi

4. Expansion of Komodo Airport, East Nusa Tenggara

5. Expansion of Radin Inten II Airport, Lampung

6. Expansion of Juwata Airport, North Kalimantan

7. Expansion of Sentani Airport, Papua

8. Expansion of Tjilik Riwut Airport, Central Kalimantan

9. Expansion of Fatmawati Soekarno Aiport, Bengkulu

10. Expansion of H.AS.Hananjoeddin Airport, Belitung Island

11. Expansion of Matahora Airport, Southeast Sulawesi

12. Expansion of Sultan Babullah Airport, North Maluku

III.1.3. Railway

1. Development of Batam Railway

2. Pulau Baai - Muara Enim Railway, Bengkulu - South Sumatera

III.1.4. Land Transportation

Not Available

III.2. TOLL ROAD

1. Batu Ampar – Muka Kuning – Hang Nadim Toll Road

III.3. WATER SUPPLY

Not Available

III.4. SANITATION

1. DKI Jakarta Sewage Treatment Plant

III. 5. TELECOMMUNICATION

Not Available

III.6. ELECTRICITY

1. Tebo Mine Mouth Coal Fired Steam Power Plant (2 x 200 MW)

III. 7. OIL AND GAS

III. 7.1. Transmission

Not Available

III. 7.2. Distribution

Not Available


*On the plus side, at least it was more accurate than the 2012 PPP book that promised 3 "ready to offer projects" and the 2011 PPP book that promised 11. Of those 12 projects, only 1 was competitively tendered through Indonesia's PPP framework, Lampung Bulk Water Supply project, but the procurement process appears to have ground to a halt.